What is a SWMS?
A SWMS, or safe work method statement, is a document that sets out the high-risk construction work being done, the hazards involved, and the control measures that will be used to manage them. Workers must follow it, and it is legally required before certain high-risk construction work starts.
High-risk construction work includes work at heights, work near unprotected edges, demolition, work on or near energised electrical installations, confined spaces, excavation over a set depth, and several other defined activities. The list and the detail come from the state or territory work health and safety regulations.
Most states and territories use the harmonised Work Health and Safety framework. Victoria uses Occupational Health and Safety law instead, with its own regulations, so a state compliance checklist or template should not assume WHS everywhere.
The SWMS should be written for the actual task and site, not copied from another job. It is prepared by the person carrying out the work, such as the subcontractor, and the principal contractor must be given a copy and check that the work is being done in line with it before it starts.
Workers should be consulted when it is prepared, and it should be reviewed and revised if the work or the conditions change. Keep a signed record that each worker has read it and understood it.
A SWMS is different from a site induction or a general risk assessment. It is a task-specific document. Regulators can ask for it at any time and may issue penalties where it is missing or not followed.