What is a progress claim?

A progress claim is a written request from a builder or subcontractor for payment for work completed so far under a contract. It is usually issued at an agreed stage or on a set date, states the amount claimed, and starts the other party's deadline to pay or respond.

In residential building the claim usually follows the contract's payment stages, for example deposit, base, frame, lock-up, fixing and completion. In commercial and civil work it is often a monthly claim against a schedule of values, showing the percentage complete for each line.

The claim is more than an invoice. Under each state's security of payment legislation, a valid payment claim triggers statutory deadlines: the person paying has a limited time to pay, or to respond in writing with a payment schedule explaining what they will not pay and why. Miss the response deadline and you may lose the right to dispute the amount. The exact timeframes and the claim requirements differ by state, so check the legislation for the state you are building in.

A claim is only as strong as the evidence behind it. Dated photos, signed variations and a clear link between the stage claimed and the contract wording are what hold up if the claim is disputed.

Residential contracts also carry limits. Deposit caps and the stages you may claim are set by state home building law, and in NSW a builder cannot claim a progress payment without the required home warranty insurance in place. Claiming ahead of the work, or for a stage not yet reached, is the most common cause of a payment dispute.

Go deeper

Related terms

General information for Australian builders, not legal advice. Rules differ by state and change over time, so check the current legislation or ask the state regulator before relying on a figure.