What is practical completion?

Practical completion is the stage where building work is finished and fit for its intended use, apart from minor defects or omissions that do not stop the owner from occupying it. It usually triggers handover, the final payment stage, and the start of the defects period.

The exact test is in the contract. Most definitions say the work is complete except for minor items that can be fixed without preventing normal use, and that any required certificates, such as the occupation certificate or equivalent, have been issued. It is not the same as perfect.

Practical completion matters because several things hang off it. The final or completion payment stage becomes claimable, any retention is usually part-released, the builder's liability for delay stops running, and the defects liability period or statutory warranty clock starts.

The common dispute is whether the job has actually reached the point. A client who believes there are too many defects will say not. A builder who claims too early risks a rejected claim and a dispute. A written inspection with a clear defects list, photos and agreed dates for rectification is the best protection for both sides.

Statutory warranty periods for residential building work, such as the time a client has to raise structural and non-structural defects, run from completion and differ by state. Record the completion date and how it was agreed so there is no argument later about when the clock started.